Dependencies


You are here: InLoox Project management glossary Dependencies

Logical sequence of activities

Dependencies describe the relationship between two or more sequential activities. These relationships determine in which order the project team needs to complete the activities. Thus, the project manager needs to identify the dependencies between activities in order to draw up the project schedule.

There are four types of dependencies:

  1. End to start: Activity B can’t start until activity A is finished
  2. Start to start: Activity B can only start if activity A has already started
  3. End to end: Activity B can only finish if activity A has finished
  4. Start to end: Activity B can’t finish until activity A starts

These dependencies are often visualized in a critical path

Would you like to receive regular info on project management topics?


Project Management Newsletter

Read more about project management on our blog


To the InLoox Blog

Our project management software InLoox helps you to make a success of your project the fast, easy and secure way


Learn more

Other terms