Color coding of the resource overview


You are here: InLoox Support Knowledge Base Online Help InLoox Web App 11.0 All Topics | InLoox Web App Resource Overview Color coding of the resource overview

InLoox reports working days as overbooked (colors yellow, red, and pink) if the effort exceeds the working time.

  • Green - Capacity available, allocation under or at 100%
  • Yellow - Allocation between 101-150% 
  • Red - Allocation between 151-199%
  • Pink - Allocation at or above 200%

The effort of the assigned tasks is distributed linearly to the working days in this period according to the time frame that InLoox calculates either from the start/end date of the task, assigned task or project.

Example: The task “Create presentation” has an effort of 5 hours. The start date is today at 2:00 PM and the end date is tomorrow at 11:00 AM. InLoox distributes the effort evenly, allocating 2.5 hours to today and 2.5 hours to tomorrow. Since the working time calendar defines working hours from 8:00 AM to 4:00 PM, today is booked at 37.5% and the following day is also booked at 37.5%. There is still capacity available on both days. The resource can take on additional tasks with a total effort of up to 5.5 hours before reaching 100% capacity.

Display of Absences/Out-of-Office Days

InLoox can display and highlight absences in the workload overview with an icon.

In order for that to work, you need to add work-free days to calendars or individual people in the InLoox settings. Read the help article Define working hours, calendars and days off