When you create dependencies, i.e. establish logical relationships between planning elements, you draw up a project schedule. To do that, you need to edit the planning elements and add details such as start and end date, duration, the type of dependency and, if necessary, set restrictions.
You can edit the planning elements in the planning list as well as in the Gantt-chart.
Overview: Types of dependencies
In order to create dependencies, you have to link the planning elements. Dependencies can be established between all planning elements (activities, summary activities, milestones).
You have several options for creating a dependency:
You can create dependencies manually in the Gantt chart:
You can also automatically link planning elements that are dependent on each other:
InLoox will automatically create a default dependency of the type "As soon as possible", based on the earliest possible start in the Gantt plan.
If you want to define other dependency types (e.g. Finish-to-Start, Start-to-Start), constraints, or time lags, you can edit the respective dependency afterwards.
NOTE Beware that InLoox will notify you of violations of constraints or inapplicable dependencies and will try to resolve these conflicts automatically, if possible.
You can also create dependencies directly in the planning table using the “Predecessor” and “Successor” columns:
Click on the line connecting two linked elements in the Gantt chart.
The dependency editor then opens, where you can make any changes, e.g. change the type of dependency or enter a time lag.
Alternatively, you can display the “Predecessor” and “Successor” columns in the planning view. To learn how to do this, see Add Columns to the Planning List.
In the corresponding field, you can define the type of dependency by positioning the green square indicators either to the left (Start = S) or to the right (Finish = F) of the element.
Example: For a Finish-to-Start dependency, the field will show the number (from column #) of the dependent planning element followed by the letters FS (Finish-Start).
You can also define a time lag. This can be done either in the Dependency Editor, or directly within the table cell by entering the offset in the following format:
add a plus or minus with a time unit (e.g., +1d for one day lag) next to the element number.
There are four different types of dependencies to link planning elements.
Finish-to-Start Dependency:
This type of dependency establishes a relationship between the end of the predecessor and the start of the successor. You ensure that the successor can only start upon completion of the predecessor.
Example: The activity “event marketing” can only start once the milestone “kick-off meeting“ has been successfully completed.
Start-to-Start Dependency:
This type of dependency restricts the start of the successor, as it can only start once the predecessor has started, too.
Example: The successor activity “partner event program“ starts at the same time as the predecessor activity “customer event program“. That means that unless the predecessor has started, the successor cannot start.
Finish-to-Finish Dependency:
This type of dependency restricts the end of the successor, as it can only end when, and if, the predecessor has been successfully completed.
Example: The predecessor “customer event program“ has to be completed at the latest on the end date of the successor “partner event program“, as the two programs have to be finalized for the creation of the event website.
Start-to-Finish Dependency
This type of dependency is only useful if you create a work-back project plan (work-back schedule). When you create a Start-to-Finish Dependency you link the start of the predecessor with the end of the successor.
Example: If a company plans to shut down a server on a certain date and move their data to a new datacenter to consolidate the hosting, they need to make sure that the new server is up and running before they can shut down the old server. Therefore, the predecessor “full-time operation new server” needs to be completed before the successor “shut off old server” can happen.
After having linked planning elements, you can set their start dates and duration. The end date of activities and summary activities is determined by when (date) they start and how long they take (duration). Milestones only have a start date – the date and time they happen.
1. To edit the planning element, select it, right-click to open the context menu, and then click Edit. A side panel opens up.
2. In the side panel you will find the field Constraint. There you can select the constraint type and date.
For example, select Start - On and set the start date.
3. You now can adjust the end date and duration of activities and summary activities.
Set the Duration of the activity by e.g. adjusting the days or by entering the end date. Alternatively, you can click the calendar icon and select the end date there.
4. You can display the duration of the planning elements in the project list by showing the Duration column.
ATTENTION InLoox has three default calendars to select from: 24/7 (continuous operation), Standard (Monday-Friday, 8 AM-4 PM) and Weekend (Saturday and Sunday, 24h). InLoox will automatically use the Standard calendar. If you want to change the calendar settings, you can do that in the InLoox settings in the section Working Times.
It is advisable to zoom in and enlarge the view to show the individual days, so that you can work comfortably in the Gantt-chart.
1. Click the Zoom In or Zoom Out button at the top to adjust the Gantt chart. Or hold CTRL while using the scroll wheel of your computer mouse to zoom in/out the Gantt chart.
2. Move the mouse over the activity or summary activity. Now navigate to the beginning or end of the activity until an arrow appears. Drag it to the left or right to expand or contract the duration.
3. If you want to change the starting date/time or end date/time, without changing the duration of the activity, you can move the activity bar in the Gantt-chart. Click on the activity bar in the Gantt-chart and move it right or left to the desired date.
If you want to delete a dependency, you have two options:
1. Select the relevant activities in the Gantt planning (hold down Ctrl) and then click the Remove dependency icon (the broken chain link) in the top navigation bar.
or
2. Double-click the connection line between the activities to open the Edit dependency window. There, you’ll find a Delete button that allows you to remove the dependency.