1. To delete a planning element, select one or more (hold CTRL) planning elements, right-click to open the context menu and select Delete activity.
2. InLoox will open a window to alert you to the fact, that you are about to:
3. InLoox also asks you, if you want to permanently delete the linked tasks from the project as well. If so, put a check mark with Permanently delete tasks from project.
4. Confirm the deletion by clicking the Delete button.
ATTENTION If you delete a summary activity, all subordinate activities are deleted as well.
WARNING The deletion of tasks cannot be undone!