If your project also includes a project time planning (Gantt chart), you can assign project-related tasks to the appropriate activity in the Gantt chart. This is particularly useful if a task is to be completed within the time frame of this activity and it is related to the content. However, you do not necessarily have to assign tasks; they can also exist as "free tasks" in the project.
To assign a task to the project schedule, please proceed as follows:
If you want to remove a task from the Gantt chart again, click on the task in the planning list and then right-click on Remove Task. The task will then reappear in the task side panel.