Public Sector Projects: Characteristics, Challenges and the 5 Phases

Public Sector Projects: Characteristics, Challenges and the 5 Phases

Because they are funded with taxpayers’ money, public sector projects attract a great deal of public interest. Frequent failures in this area draw plenty of criticism, yet much of it could be avoided.

What Makes Public Sector Projects Special

Our world is in a state of constant change. Megatrends such as urbanization and digitalization demand continuous, fundamental change. This change does not only take place in the private sector; public administration has to address it as well. Political decision-makers set the direction of the transformation, and it is ultimately up to public administration to implement it. Unlike in business, such projects are not financed by realized profits or borrowed capital, but by tax revenue. The projects are made possible by the financial resources of the population. This leads to the following characteristics:

1. High Public Interest in Public Sector Projects

Since public administration projects are financed with public funds, citizens have a legitimate interest in them. A failure or a significant budget overrun, as seen with Berlin Brandenburg Airport (BER), is perceived by the public as a loss and causes resentment. Because of this high level of interest, public sector projects also receive comparatively high media attention. Irregularities are often quickly uncovered and made public by journalists. Accordingly, not only the decision-makers but also those responsible for the project are under public pressure. Conscientious, transparent and, above all, realistic planning therefore becomes more important. How closely planning matches reality leads to the next characteristic of public projects:

2. A Tendency Toward Tight Cost Estimates

Public projects, such as the construction of a new section of highway, must be approved before they can be carried out. To obtain approval, the project should appear as attractive, that is, as inexpensive as possible. In addition, public institutions in Germany are bound by the principles of economy and thrift (Section 7 (1) of the Federal Budget Code). Work must therefore always be put out to tender. Since the lowest bidder wins the contract, costs are deliberately estimated tightly here, too. Overly optimistic cost estimates are thus often a central feature of public projects.

3. Lack of Expertise

Projects run by public institutions are by no means rare. At any given time, projects financed by public money are underway. Nevertheless, expertise in managing such projects is often lacking. The reason is that they are organized and carried out in a decentralized way. Individual agencies often have relatively little experience and limited subject matter and project management expertise. This is an aggravating factor.

4. Conflicting Goals

In the private sector, the overall objective is relatively clear in most cases. Projects are carried out to contribute to achieving the company’s goals. In the complex political environment in which public projects are implemented, things are not that simple. The interests of many stakeholder groups have to be reconciled. Sometimes a compromise is reached. Often, however, certain interests are not taken into account. One example is the debate about wind turbines for power generation. Political decision-makers want to achieve energy independence or a more environmentally friendly power mix, for example. Some residents near potential sites, on the other hand, want to preserve the landscape. Satisfying both interests equally is often hardly possible.

Although there is a great deal of overlap with private sector projects, public sector projects have some specific characteristics. Above all, the stakeholder groups differ greatly. After all, taxpayers, legislators, the political opposition and other groups also have a legitimate interest. In addition to the tendering requirements mentioned, public administration is subject to further regulations and guidelines that constrain the project team to a certain extent. The political relevance and the influence of political and media interest groups should not be underestimated either. And even defining a clear goal is often a challenge in itself.

A Practical Guide to Successful Project Completion

To help public administration master the challenges of managing public projects, the German federal government has published a practical guide to project management (in German). It is aimed primarily at business and IT projects, but because it is worded in relatively general terms, it can largely be applied to other scenarios. The guide also explicitly points out that the phase model must be adapted to the needs of each project. Each phase ends with a result that serves as the basis for the next phase, creating a holistic process.

Phase 1: Initiation

The initiation phase is about roughly outlining the upcoming project. The project idea is discussed, and possible objectives are presented and debated. The assignment of responsibilities also receives initial attention. The phase ends with a project outline.

If the project is, for example, the construction of a highway bridge, the team discusses why the bridge makes sense at all and which problem it is meant to solve. A first rough objective might be smoother traffic flow. The project outline contains an approximate time frame, a short description and other key points such as the approximate funding requirement.

Phase 2: Definition

The federal government’s project model has two planning phases. The first is the definition or high-level planning phase. The project outline from the previous phase is fleshed out and clear objectives are formulated. The core team, consisting of the project manager and the key people responsible, is appointed. In addition, milestones are set, effort is estimated and the project environment is analyzed. Finally, the objectives are discussed in this phase and the positions of those involved are recorded. Care is essential here, not least when jointly assessing feasibility. The phase ends with the project definition, which is decisive for further planning.

In our example, this is where the core project team is appointed. The project manager should have experience with transportation infrastructure projects. Civil engineers are also needed, and possibly contract managers to bring subcontractors on board. The objectives are made more specific; for example, the team might aim for 15 percent more traffic capacity with a four-lane highway bridge.

Phase 3: Planning

The second planning phase is detailed planning. A sequence plan, a schedule and finally a work breakdown structure are created. In addition, resource allocation is planned, risks are analyzed and the project’s cost-effectiveness is reviewed. In short, all relevant aspects of the project are precisely defined in this planning phase. This is documented in the project plan or project manual.

In our example project, the specific start date is set here. The sequence of the various tasks, such as the delivery of components, the construction of the foundation and finally the marking of the finished roadway, is then clearly defined. Gantt planning can be useful here: it shows all tasks and their dependencies and makes potential bottlenecks visible. With suitable project management software, external service providers such as construction companies can also view the plan, which prevents misunderstandings.

Phase 4: Execution and Control

The next step is the most important part of the project. The project team works through the plan step by step. The result of this phase is the finished product or the agreed service. In most cases, this phase is further divided, with milestones that each deliver an interim result. A central aspect of this phase is project controlling: the team continuously tracks where the project stands and whether progress matches the plan. If it does not, appropriate measures must be taken.

In our example, this phase begins with the groundbreaking and ends with the opening of the bridge. To make sure everything runs smoothly in between, project progress must be monitored carefully and continuously.

Phase 5: Closure

Once the project deliverable has been successfully completed, the project can be closed. A final meeting is held, resources are released and the project organization is dissolved. The result of this phase is the final report.

In our example, too, the final project report is very important. In addition to results, costs and many other key aspects, it records the problems that occurred. Documentation helps avoid them in the future and is therefore essential for learning.

The phase model described is the standard approach for public administration projects in Germany, but it is not mandatory in this form. Depending on the scope of the project, phases can be combined, in many cases the first two phases or phases three and four.

How public administration is modernizing and what can be learned from failed megaprojects is the subject of Public Sector Projects: Modernization and Lessons from Failed Megaprojects.

Keep reading in the InLoox blog.