Add lag to planning elements | InLoox 9 for Outlook


You are here: InLoox Support Knowledge Base Online Help InLoox for Outlook 9.0 All support articles | InLoox 9 for Outlook Project planning | InLoox 9 for Outlook Add lag to planning elements | InLoox 9 for Outlook

In certain instances, you may want to include some buffer to account for delays or external factors that affect your project. In this case, you can add lag in your project plan. Lag times can also serve as a kind of time constraint between planning elements.

 

1. Double-click on the link that connects two planning elements to open the window Edit Dependency.

2. Add lag in work days or hours and minutes. 

InLoox planning

3. You can also add lead time. Click on Negativ when the successor can start before the predecessor is completed. 

InLoox planning